Project Completed October 2017
This project consisted of the milling of existing asphalt and overlaying with new pavement material along Waleska Way from Arrowood Drive to Dodson Drive
The milling and overlaying of Arrowood Drive, Tyewood Lane, Waleska Way, and Branchwood Drive were combined and collectively named EP-002 Arrowood and Surrounding Streets.
The contract was awarded to Mullins Brothers Paving Contractors. For more information on this project please contact Cadell Hall, Engineer II, at (404) 669-4321 or chall@eastpointcity.org or Vincent Reynolds, Transportation Manager at (404) 270-7114 or vreynolds@eastpointcity.org .
Purpose/Project: Tier 1 Maintenance and Safety Enhancements
Department | Public Works |
Budget | $596,400.00 - Combined (EP-002) |
Funding Source | TSPLOST |
Spent | $368,264.74 - Combined (EP-002) |
Estimated Start Date | September 2017 |
Estimated Completion Date | October 2017 |
Project Manager | Cadell Hall and Vincent Reynolds |