Project is in construction. Awarded to Baldwin Paving.
Each year the Georgia Department of Transportation (GDOT) notifies all local governments of the upcoming “Local Maintenance Improvement Grant” (LMIG) program, if funding is made available. The LMIG program requires a 30% Local match from the municipality..
This project consists of the milling of existing asphalt and overlaying with new pavement material, and installing new header curb along the following streets:
For more information on this project please contact Cadell Hall, Transportation Division Manager, at (404) 669-4321 or chall@eastpointcity.org
Purpose/Project: Local Maintenance Improvement Grant – Resurfacing
Department | Public Works |
Budget | $669,838.33 |
Funding Source | LMIG (30% Local Match) |
Spent | $497,834.41 |
Estimated Start Date | April 2020 |
Estimated Completion Date | June 2020 |
Project Manager | Cadell Hall |