Details

Currently Under Design.  Contract Awarded to Atkins.

The current T-Intersection has a skewed alignment which causes safety issues for multiple approaches. The goal of this project is to design improve the safety and operation at this location. Concepts for improvement will consider:

  • Realignment of the intersection
  • Pedestrian facility improvements
    • Relocating existing MARTA bus-stop, relocating existing crosswalk, ADA ramp upgrade

The contract was awarded to Atkins. For more information on this project please contact Cadell Hall, Transportation Division Manager, at (404) 669-4321 or chall@eastpointcity.org .

 

 


Department Public Works
Budget $250,000
Funding Source TSPLOST
Spent $188,461
Estimated Start Date Summer 2022
Estimated Completion Date TBD
Project Manager Cadell Hall and Jeremy Goodwin

Map

Address

4074 Washington Road 

More Info.

Project Status

Planning