Project Completed October 2019.

The goal of Phase 1 of this project is to provide sidewalks along the east side of Sylvan Road from Cleveland Avenue to Jefferson Avenue. This project will include crosswalks striping, ADA Ramps, and repair of broken sidewalks and curb where needed.

For more information on this project please contact Cadell Hall, Transportation Division Manager, at (404) 669-4321 or chall@eastpointcity.org .


Department Public Works
Budget $372,825.00
Funding Source Capital
Spent $372,825.00
Estimated Start Date August 2019
Estimated Completion Date October 2019
Project Manager Cadell Hall and Vincent Reynolds