EP-006 Dodson Drive and Surrounding Streets – Resurfacing

Details

 

This project consists of the milling of existing asphalt and overlaying with new pavement material, and installing new header curb along the following streets:

  • Arlington Road (Washington Rd to Potomac Dr)– Completed
  • Ben Hill ( Headland to City Limit) – Completed
  • Ben Hill Avenue (Charles Dr to Leigh Circle) – Completed
  • Ben Hill Dr ( Patching) – In Progress
  • Bonnybrook Way (Headland Dr to City Limits)– Completed
  • Calmer Circle (Charles Dr to Charles Dr)– Completed
  • Caroll Court (Charles Dr to Dead End)– Completed
  • Carriage Way (Charles Dr to Washington Rd)– Completed
  • Charles Drive (Washington Rd to Dead End)– Completed
  • Cherry Laurel Lane S.W. (Connally Dr to City Limits) – Completed
  • Cheseapeake Way (Arlington Rd to Potomac Dr)– Completed
  • Cheviot Glen (Cul-de-sac to Headland Drive) – Completed
  • Church St ( Washington Rd to W Forrest) – Completed
  • Dejarnette Dr (Meadow Lark Dr to Dead End) – Completed
  • Delowe Dr ( Delowe Stanton Access Rd to Ellenwood Dr) – Completed
  • Dodson Dr (Dodson Dr Connector to SR 166)– Completed
  • Dodson Dr Connector ( Dodson Dr to Washington Rd) – Completed
  • Dodson Lee Drive (Dodson Dr to Dead End) – Completed
  • Dodson Terrace (Washington Rd to West Rugby Av)– Completed
  • Headland Dr (City Limits to Paul D West) – Phase 1 Resurfacing – Completed
  • Leigh Circle (Charles Dr to Charles Dr)– Completed
  • Leith Ave (Wood Valley Dr to Plantation Dr) – Completed
  • Maxwell Dr (Headland to City Limit) – Completed
  • McAlpine Drive (Cul-de-sac to Headland)– Completed
  • Meadow Lark Dr (Rolling Brook Trl to Hogan Rd) – Completed
  • Mount Olive Road (Washington Rd to Dead End) – Completed
  • Philadelphia Place (Dead End to Arlington Rd)– Completed
  • Revere Court (Dead End to Arlington Rd)– Completed
  • Rolling Brook Trail (Dodson Dr to Dead End) – Completed
  • Spain Drive (Dodson Lee Dr to Dead End) – Completed
  • Stoneview Terrace (Mt. Olive Rd to Dead End) – Completed
  • West Potomac Drive (Arlington Rd to Washington Rd)– Completed

 

For more information on this project please contact Cadell Hall, Transportation Division Manager, at (404) 669-4321 or chall@eastpointcity.org

 

Purpose/Project: Maintenance and Safety Enhancements


Department Public Works
Budget $5,369,783.15
Funding Source TSPLOST
Spent $5,369,783.15
Estimated Start Date Fall 2019
Estimated Completion Date December 2020
Project Manager Cadell Hall and Jeremy Goodwin

Map

Address

3152 Dodson Drive 

More Info.

Project Status

Conclusion

Photos